A MagicPlan-style export, notes, and diagrammatic site evidence become a reviewable existing-condition record.
Where this starts: a phone walk and an export
Before any of the screens in this workspace exist, somebody stood in the building. magicplan is one common way that walk gets captured, and it is the one shown here. If your crews capture another way, the export changes and nothing else does.
Walk the space with a phone
One person, no tripod and no laser. Room by room, plus photos of the conditions that matter: panels, congested ceilings, damage, access.
magicplan turns it into a measured export
A report PDF carrying the sketch, the dimensions, your photos, your notes and your own custom forms. A sketch PDF. A DXF that opens in AutoCAD or SketchUp. Claims work can go straight to Xactimate or Cotality.
The export lands here
This is the step almost everybody does by hand. Instead of a person retyping the export into an estimate at nine at night, every line arrives with its source attached and a review state.
In a live deployment this is where your own export lands. This workspace is a demonstration, so it will not take a real file: never put an actual client project into a demo. Load the synthetic one instead and watch what happens to it.
Your tools stay where they are. The export is the input. Where the reviewed result goes afterward is whatever you already run on, and that is the part worth thirty minutes of talking rather than guessing.
Area view · east corridor
Needs MEP review9'-2" ceiling
panel LP-2
protect in place
roof access
Evidence rail
Diagrammatic synthetic evidence
Diagrammatic synthetic evidence
Diagrammatic synthetic evidence
Diagrammatic synthetic evidence
Diagrammatic synthetic evidence
Diagrammatic synthetic evidence
| Line | Area | Captured condition | Source | Output consequence | Review |
|---|---|---|---|---|---|
| 001 | East corridor | Ceiling height 9'-2" | HP-001 | Existing-condition baseline | Confirmed |
| 002 | East corridor | Congested plenum at grid E4-E6 | HP-002 | Constructability flag | Needs MEP review |
| 003 | Electrical room | Existing panel LP-2; directory incomplete | HP-003 | Field verification hold point | Open |
| 004 | East corridor | Existing fire-alarm device conflicts with new ceiling layout | HP-004 | Fire alarm / RCP coordination | Open |
| 005 | Roof | Access hatch blocked during occupied hours | HP-005 | Access constraint + work-window rule | Confirmed |
| 006 | East corridor | Damaged ceiling grid; 34 LF observed | HP-006 | Quantity + allowance review | Needs quantity check |
| 007 | Drawing comparison | Addendum 2 reroutes conduit through congested zone | A3 + ADD-02 | Electrical scope impact | Open |
| 008 | Permit review | AHJ asks for revised circuit/load note | PC-07 | Permit response blocker | Open |
| 009 | Owner decision | Acoustic tile alternate not selected | OD-04 | Ceiling release blocker | Open |
| 010 | Bid coverage | Fire protection has one qualified proposal | FP-01 | Coverage-risk flag | Open |
Existing-condition record ready for review
10 facts retain source, area, capture date, confidence, review requirement, affected package, and current state.