Addendum 2 · Source lineage
One source change is traced through scope, coordination, permit, price, and release.
Revise east corridor branch-conduit routing
Route branch conduit north of grid E4-E6 to avoid the existing duct bank. Coordinate the fire-alarm device and reflected ceiling plan. Revise the circuit/load note in the permit response.
ADD-02 / PAGE 2 / NOTE E-4
Captured Aug 8 · Casey Morgan
Confidence: high · review requiredWhy this matters
The route enters the exact zone field evidence HP-002 marked as congested. The change therefore cannot stay inside the drawing register; it propagates to the packages, allowance, permit response, and release milestone.
The system may propose the impacted records. It cannot make the design judgment or release field work.
Electrical package
Owner: Eli Brooks · Due: Aug 12
Exact source: Addendum 2, page 2, note E-4; drawing A3 east corridor overlay; evidence HP-002.
ADD-02 → A3/E4-E6 → electrical-package → human review requiredProposed next action
Eli Brooks schedules a 20-minute MEP overlay review by Aug 12, attaches the marked A3 route, and routes the result to Casey and Priya.